YORK RD LAFO (Grand Ave to Green St)

The Village of Bensenville is about to undertake a very significant roadway resurfacing project in your area. York Road will be resurfaced from Grand Ave to Green St. As part of the same project, the Village will also perform spot C&G repairs, spot sidewalk repairs, ADA improvements, pedestrian push button signals, pavement patching, structure adjustments, traffic detector loops, parkway restorations, pavement markings, and other miscellaneous items necessary to complete the project. 

The total project cost is estimated to be around $2.15 million including design, construction and construction engineering. The Village has received approximately $1.22 million in federal grant monies towards the construction of this project. 

The project consists of removing 4.5 inches existing hot-mix asphalt amounting to approximately 51,000 square yards of pavement removal which will be replaced with 6,500 tons of hot-mix asphalt binder plus 5,800 tons of hot-mix asphalt surface course. As part of the project, approximately 3,900 feet of C&G will be repaired as well 5,900 square feet of sidewalk... READ FULL INFORMATION LETTER.

Update 04/19/19

During the week of April 15, the contractor continued with saw-cutting, removing and replacing concrete C&G and sidewalk ramps along the east/west side of York Rd. Weather permitting, during the week of April 22, they will continue to do the same work along the east and west side of York Rd. There will be other sub-contractors onsite as well performing work items such as brick pavers, guardrails installation, etc.  The work will be performed under daily lane closures. The impacted residents who will not have driveway access during this operation have been notified. The contractor plans to utilize high-early concrete mix to get the driveway access open within 24-hrs of the pour.

Update 04/12/19

During the week of April 8, the contractor begin saw-cutting, removing and replacing concrete C&G and sidewalk ramps along the east side of York Rd. During the week of April 15, weather permitting, they will continue to do the same work along the east and west side of York Rd. There will be other sub-contractors onsite as well performing work items such as brick pavers, guardrails removal, etc.  The work will be performed under daily lane closures. The impacted residents who will not have driveway access during this operation have been notified. The contractor plans to utilize high-early concrete mix to get the driveway access open within 24-hrs of the pour