Church Road Reconstruction - Jefferson to Grove Ave
The Village of Bensenville is about to undertake a very significant roadway reconstruction project in your area. Church Road will be reconstructed from Jefferson St to Grove Ave. As part of the same project, the Village will also construct an off-street 8-feet wide shared use path to accommodate pedestrians and bicyclists. Other infrastructure improvements included in this project are curb and gutter, storm sewers, watermain replacement, new water services from the watermain to the b-box, driveway aprons, parkway restorations, pavement markings, and other miscellaneous items necessary to complete the project. The tentative start date for the project is set for early to mid-May 2017 with a substantial completion of November 15, 2017. Daily work hours are from 7:00AM to 7:00PM, Monday thru Friday. Saturday work hours will be limited from 7 AM – 3 PM. The project is designed to be constructed in multiple stages to keep one-way (southbound) traffic open at all times during construction. Please note, there will be some temporary delays during construction hours due to various contractor activities. If possible, it is highly recommended to avoid the construction area.

Download Information Letter No. 1

Update 06/30/2017
The contractor has installed C&G on the west side of Church Rd from Jefferson to 2nd Ave this week along with the driveway aprons in the same stretch. The driveway aprons require a minimum of 72-hours of cure time and will be re-open to the impacted residents after the Independence day weekend. The impacted residents can park their vehicles in the construction zone in front of their homes until the driveways are re-opened. Temporary access has been provided. The contractor also continued to perform roadway excavation from Grove Ave to Wood Ave. The sewer contractor worked on installing mainline storm sewer this week.

After today June 30, 2017, there will be no work on this project until the State of Illinois has an approved budget. There will be no work on July 3 and 4, even if the State has reached a budget deal. The contractors will continue to work on pavement removal, earth excavation and underground improvement when work resumes.

Utility companies will continue their work within the project area as they are not impacted by the state budget impasse. Nicor is anticipated to complete their work by July 21, 2017. AT&T has yet to begin their work on the project and can cause delays to overall project completion.

Update- 06/16/2017
the underground contractor continued to install mainline storm sewer this week along Church Rd. A second underground crew installed storm sewer laterals from Grove Ave to Wood Ave. The general contractor begin pavement excavation on the west side of Church Rd just north of 2nd Ave. Weather permitting, these operations will continue during the week of June 19, 2017. NPL (working for Nicor) continued to install the new gas main throughout the project corridor and will continue to do so next week. Other utility companies such as Comcast and AT&T also have work that needs to be completed within the project corridor. With different contracts working in different areas along the project corridor, keeping southbound traffic open to through traffic is difficult and a detour around the project site for southbound traffic will be in effect. Contractor will continue to keep project site accessible to local residents and emergency vehicles.

Update- 06/12/2017
The contractor will continue with the installation of mainline storm sewer from Wood Ave heading south during this week. The general contractor is tentatively scheduled to begin pavement removal on the west side of the street from Jefferson to 2nd Ave this week. Intermittent detour routes will be effective on daily basis to route traffic around the construction zone. Please avoid the project area if possible.

Project Update 06/02/2017
Weather permitting, during the week of June 5, 2017, the contractor will continue with the underground storm sewer installation. Nicor’s sub-contractor NPL will be working onsite to install gas mains within the project limits. Other utility companies such as Comcast is also tentatively scheduled to relocate its overhead facilities. Please avoid the construction zone if possible.

On Monday June 5, 2017, the underground crew will be installing watermain across the intersection of Church Rd/2nd Ave. Traffic will not be able to get through the work zone during this installation. Access will be maintained for the residents impacted by the closure as well as emergency vehicles. The attached detour map will go into effect at 7 AM on 6-5-17. At this time, we anticipate the underground crew to finish the watermain work on 6-5-17 barring any other conflicts.

Church Second Av Detour

Project Update 05/25/2017
The contractor installed storm sewer from 2nd Ct to Jefferson St this past week. The contractor will begin storm sewer installation between 2nd Ct and 2nd Ave week of May 29, 2017. Weather permitting, the contractor is anticipating to be installing storm sewer at the intersection of Grove Ave/Church Rd starting May 31, 2017. We anticipate the contractor to be there for 3-4 days barring any unforeseen circumstances. There will be space for traffic around the work zone in the east-west direction on Grove Ave, but it will be tight. The contractor also plans to use flaggers to assist during this operation.

Church Grove Traffic Shift Configuration
Detour Map


Project Update 05/11/2017
The start of project has been slightly delayed due to rain over the past couple of weeks. Weather permitting, the underground contractor is scheduled to begin excavation and storm sewer installation the week of 5/15/17. One crew will start at Grove Ave and work its way south. Second crew will start working at 2nd Ct and work its way south. The detour route will remain the same. Please avoid construction zone if possible.

ComEd crew will continue working onsite to relocate its facilities. AT&T and Nicor have submitted their respective permits to relocate their facilities within the project corridor. Project team is identifying ways to work with the utility companies to accommodate the proposed utility relocations while continuing to keep the project on schedule.

Project Update 04/27/2017
Weather permitting, the traffic detour is scheduled to go into effect on May 1, 2017. Church Road within the project limits will be closed to northbound traffic.

Weather permitting, the underground contractor is to begin storm sewer installation starting the week of May 1, 2017. One crew will start at Grove Ave and work its way south while the other crew will start at Jefferson St and work its way north. During construction hours, for safety reasons, a minor southbound traffic detour will be posted to get around the block to accommodate storm sewer installation. Access to local traffic (properties fronting Church Rd), school buses and emergency vehicles will be maintained during construction. Please avoid the project area unless absolutely necessary.

Detour Map