2019 MFT HMA Paving Project

The Village of Bensenville will be undertaking a resurfacing project this summer. The focus of the project will be on Grove Ave (IL-83 to Church Rd) and Foster Ave (Village limits to Il-83). The Village will be resurfacing these two streets along with spot sidewalk, C&G improvements. It will also include striping and landscaping. As part of the project, the Village will also be patching other residential streets. The project has been awarded to Schroeder Asphalt Services of Huntley, IL. Tentatively, we are expecting a mid to late June start for this project. The completion date is August 2, 2019.  View Location Map and  Information Letter 1 - Start of Construction

locationMap_Snap Opens in new window

Update 08/09/19

During the week of Aug 5, the concrete contractor worked on removing C&G and sidewalk on Grove Ave and Foster Ave. They also poured C&G as well as sidewalk on Grove Ave. There is a possibility that the contractor may perform the Milling on Grove Ave on Saturday 8-10-19 but a firm confirmation has not been provided. During the week of Aug 12, the contractor will plan to mill, pave and stripe both streets.

Update 08/01/19

There was no work during the week of July 29. The general contractor is bringing in a new concrete sub-contractor for this project. The project deadline is Aug 2 and we’ve informed the general contractor that liquidated damages will begin after Aug 2 on this contract. The village has also put a hard deadline of getting Grove Ave completed by Aug 12. First day of school is Aug 14. The general contractor has not yet provided a schedule as to when they will begin work on remainder of the project.  

Update 07/25/19

There was no work during the week of July 22. The concrete contractor is still apparently backed up on his current jobs and is tentatively scheduled to be onsite during the week of July 29, weather permitting.

Update 07/19/19

There was no work during the week of July 15. The concrete contractor is still apparently backed up on his current jobs and is tentatively scheduled to be onsite during the week of July 22, weather permitting.

Update 07/12/19

There was no work during the week of July 8. The concrete contractor is still apparently backed up on his current jobs and is scheduled to be onsite during the week of July 15, weather permitting. There will be no work during the week of July 15.

Update 06/21/19

A pre-construction meeting was held on May 30th. The tentative start date for the contractor has been postponed to June 24th.  

Update 06/07/19

A pre-construction meeting was held on May 30th. The tentative start date for the contractor is June 17th.  

Update 5/31/19

A pre-construction meeting was held on May 30th. The tentative start date for the contractor is June 17th.  

Update 5/24/19

The staff is awaiting contractor to confirm a pre-construction meeting date. At this time, we are anticipating this project will begin mid to late June.