LS-13 (Supreme Dr) and LS-17 (Spruce Ave) Rehabilitation

The Village owns and maintains sanitary sewer lift stations at Supreme Dr (just north of N. Frontage Rd) and Spruce Ave (@ Twin Oaks St). Both of these lift stations are integral part of the Village’s sanitary sewer collection system and are scheduled for rehabilitation work in 2020. Both of these lift stations will receive mechanical and electrical upgrades along with some piping as well as wet well rehabilitation. This locally funded project will begin early May 2020 and will be substantially completed by Aug 14, 2020. The final completion date is September 30, 2020.

Read full project information letter.

GIS Bensenville Construction Story Maps

Update 08/07/2020

During the week of Aug 3, 2020, the contractor finished demolition At Spruce LS and installed all new piping in the wet well and valve vault along with applying cementitious coating inside the wet well. The electrical contractor begin prepping for installation of the control panel. Weather permitting, during the week of Aug 10, the contractor will continue working on electrical items at Spruce lift station while the general contractor will begin demolition at Supreme LS as well as setup bypass pumping.

Update 07/31/2020

During the week of July 27, 2020, the contractor installed and put in operation bypass pumping at the Spruce lift station. The contractor also began demolition of existing lift station components. Weather permitting, during the week of Aug 3, the lift station demolition will continue along with installation of new piping inside the wet well and valve vault.