2020 MFT HMA Pavement Program

The Village of Bensenville is about to undertake a general maintenance contract in the vicinity of your residence. As part of this project, the Village will be resurfacing Grove Ave (Church Rd to Mason St), Plentywood Lane and W Green St (Fenton HS to Church Rd). On these three streets, the Village will also perform spot C&G repairs, spot sidewalk repairs, ADA improvements, pavement patching, structure adjustments, , pavement markings, landscape restoration and other miscellaneous items necessary to complete the project. As part of the same project, the Village will also be performing surface patches on other streets to prolong the life of the existing pavement. Please see the map below depicting the streets where the Village plans to perform pavement patching. Read full information letter.

HMAPaving_2020map Opens in new window

Update 08/07/2020

During the of Aug 3, 2020, the contractor did not perform any work.. Any landscaping related issues will be addressed in mid to late September 2020.

Update 07/31/2020

During the of July 27, 2020, the contractor was issued a punch list of items to be addressed. Any landscaping related issues will be addressed in mid to late September 2020.

Update 07/16/2020

During the week of July 13, 2020, the contractor worked on installation of pavement markings as well as village wide patches. The project will be complete on July 17, 2020.

Update 07/09/2020

During the week of July 6, 2020, the contractor installed HMA surface on Plentywood, Grove and W Green St. During the week of July 13, the contractor will perform pavement marking and village wide patches at various locations.  

Update 06/26/2020

During the week of June 22, 2020, the contractor performed miner structure adjustments. Weather permitting, during the week of June 29, 2020, the contractor plans perform parkway restorations and plan to place HMA surface on all three streets.  

Update 06/19/2020

During the week of June 15, 2020, the contractor worked on grinding pavement on Grove Ave, Plentywood Lane, and W Green St. They also performed patching on Plentywood Lane.

Weather permitting, during the week of June 22, 2020, the contractor plans to perform the structure adjustments and parkway restorations. They also tentatively plan to place HMA surface.

Update 06/12/2020

During the week of June 8, 2020, the contractor worked on removing and replacing spot sidewalks as well as spot curb and gutter on all three streets. The cure time on concrete is 72-hours before impacted residents can get back in their driveways. The contractor plans on having a crew come by Saturday June 13 to open up impacted driveways. Weather permitting, during the week of June 15, 2020, the contractor tentatively plans to grind and overlay the three streets as well as perform Village wide patching.

Update 06/05/2020

This project will include Grove Ave (Church Rd to Mason St), Plentywood Dr and W Green St (Church Rd to Fenton HS). These streets will receive spot C&G repairs, spot sidewalk repairs and pavement resurfacing. As part of the project, there will be surface patching done throughout the Village as well. The tentative construction start date is postponed to week of June 8, 2020. The project has a July 17, 2020 substantial completion date.

05/29/2020

This project will include Grove Ave (Church Rd to Mason St), Plentywood Dr and W Green St (Church Rd to Fenton HS). These streets will receive spot C&G repairs, spot sidewalk repairs and pavement resurfacing. As part of the project, there will be surface patching done throughout the Village as well. The tentative construction start date is week of June 1, 2020. The project has a July 17, 2020 substantial completion date.

05/22/2020

This project will include Grove Ave (Church Rd to Mason St), Plentywood Dr and W Green St (Church Rd to Fenton HS). These streets will receive spot C&G repairs, spot sidewalk repairs and pavement resurfacing. As part of the project, there will be surface patching done throughout the Village as well. The tentative construction start date is June 1, 2020. The project has a July 17, 2020 substantial completion date.

05/15/2020

The staff held a pre-con meeting conference call during the week of May 11, 2020. This project will include Grove Ave (Church Rd to Mason St), Plentywood Dr and W Green St (Church Rd to Fenton HS). These streets will receive spot C&G repairs, spot sidewalk repairs and pavement resurfacing. As part of the project, there will be surface patching done throughout the Village as well. The tentative construction start date is June 1, 2020. The project has a July 17, 2020 substantial completion date.