Crestbrook Subdivision Roadway Reconstruction Project

PROJECT SCOPE

This Spring the Village will reconstruct residential roadways and install street lighting in the Crestbrook Subdivision.  This includes Addison Road, Center Street, Woodland Avenue, Forestview Drive, and Forestview Road.  The project also includes driveway apron removal and replacement, drainage structure adjustment/reconstruction, new drainage structures, addition of ribbon curb, pavement markings, and landscape restoration within the right-of-way.  The construction activities are generally broken down into three phases:

  • Drainage Repairs – Necessary repairs and/or modifications are made to drainage structures, driveway culverts, and roadside swales/ditches along roadways.
  • Roadway Improvements – Removal of the existing pavement shoulders, and driveways.  Construction of the proposed ribbon curb, driveway aprons, and initial asphalt pavement layer.  Streetlighting infrastructure will be installed.  This work is generally limited to one side of the street at a time to allow access to their property.  
  • Pavement Repairs – The final phase includes parkway restoration, placement of the final pavement surface layer, and then final pavement markings are placed.  Streetlights will be installed and turned one.  Prior to paving, a tack-coat of fresh oil is applied as an adhesive or bonding between the asphalt layers. Fresh oil signage will be posted in advance to remind motorist to travel slowly on the tack-coat material. 

During construction, traffic will be maintained with daily lane closures and flaggers.  Only the immediate works zone area will be closed during working hours.  The project is expected to be substantially completed by late August 2023, with final completion and landscape restoration completed by October 27, 2023.  

Project Details

Contract Bid Date: April 4, 2023, 11:00 A.M
Contract Award Date: April 25, 2023
Project Cost: TBD
Awarded Contractor: TBD
Construction Start Date: Late Spring 2023
Construction Completion Date: October 27, 2023
Funding Sources: Capital Improvements Fund

Project Contact Information

Village of Bensenville Resident Engineer
Brad Hargett, P.E. TBD
Assistant Village Engineer TBD
Email: bhargett@bensenville.il.us Email: TBD
Phone: 630-350-3411 Phone: TBD

Project Documents

Name Link to Document
Notice to Bidders View
 

Project Updates

(Future weekly updates to be started here, most recent update first)