Irving Park Rd Streetscape Project Phase III
PROJECT SCOPE
This Fall the Village will continue efforts to improve one of the major vibrant business corridors within the Village of Bensenville limits. The Village will be undertaking Phase III of the streetscape improvement project along portions of Irving Park Road. Previously, the Village completed Phase I & II of a multiple phased construction project with decorative streetlights and stamped colored sidewalk.
Phase III construction activities include installing a seven-foot-wide stamped concrete sidewalk along the north side of Irving Park Road from Church Road to west of Addison Street. The scope of work also includes installation of new driveway aprons (where disturbed by sidewalk improvements), structure adjustments, retaining wall replacement, and spot curb and gutter repairs.
During construction, traffic will be maintained with daily lane closures and flaggers. Only the immediate works zone area will be closed during working hours. The project is expected to be substantially completed by late October 2023, with final completion and landscape restoration completed by November 30, 2023
Project Details
Contract Bid Date: | August 8, 2023, 11:00 A.M |
Contract Award Date: | August 22 2023 |
Project Cost: | $467.793 |
Awarded Contractor: | Everlast Blacktop, Inc |
Construction Start Date: | September 2023 |
Construction Completion Date: | November 30, 2023 |
Funding Sources: | Capital Improvements Fund |
Project Contact Information
Village of Bensenville | Resident Engineer |
---|---|
Brad Hargett, P.E. | Christian Haas |
Assistant Village Engineer | Gonzalez Companies, LLC |
Email: bhargett@bensenville.il.us | Email: chaas@goco.net |
Phone: 630-350-3411 | Phone: 690-800-6090 |
Project Updates
9.22.2023
This week, the contractor Everlast Blacktop continued concrete work with pouring new stamped concrete sidewalks, concrete curbs, and driveways. Next week, Everlast will continue removals and pouring new concrete curbs, driveways, and stamped concrete sidewalks. During construction, traffic will be maintained with daily lane closures and flaggers. Only the immediate works zone area will be closed during working hours.
9.15.2023
This week, the contractor Everlast Blacktop continued concrete work with pouring new stamped concrete sidewalks, concrete curbs, and driveways. Next week, Everlast will continue removals and pouring new concrete curbs, driveways, and stamped concrete sidewalks. During construction, traffic will be maintained with daily lane closures and flaggers. Only the immediate works zone area will be closed during working hours.
9.8.2023
The contractor, Everlast Blacktop, began mobilizing to the project site. Pre-construction work has begun on the project with advanced warning signs erected and project layout. They also initiated construction at the end of this week with concrete saw cutting and retaining wall removal. Next week, Everlast will begin removing concrete curbs and driveways. It is anticipated that by the end of next week new concrete curb will begin to be poured. Businesses will be notified when access to their driveway will be restricted. During construction, traffic will be maintained with daily lane closures and flaggers. Only the immediate works zone area will be closed during working hours.
9.5.2023
This week, construction activities are expected to begin. Project start date is September 7, 2023.