2018 Village Watermain Improvements

This locally funded project will replace approximately 3,300 linear feet of water main on the 400 blocks of Rose, May, and Grace Streets, along with Washington Street from York Road to Marion Street. As part of this project, the Village will also be replacing water service up to the existing b-box, conducting spot curb and gutter repairs, spot sidewalk repairs, and roadway resurfacing. In addition, driveway aprons impacted by the construction will be replaced, parkways will be restored, and other miscellaneous items will be addressed as necessary. The project is expected to start on April 2, 2018 with a final completion date of September 28, 2018. A project information letter is attached.

Download Information Letter No. 1

Update 04/20/18

During the week of April 16th , the contractor finished installation of 8-in watermain on Grace St along with some storm sewer manhole reconstruction. During the week of April 23, the contractor is tentatively scheduled to begin watermain installation on May St and/or Rose St, depending on passing the pressure test of the new main on Washington St.

Update 04/13/18

During the week of April 9th , the contractor finished installation of 8-in watermain on Washington St. Weather permitting, the contractor will continue to install new watermain down Grace St during the week of April 13 as well as pressure test and chlorinate the watermain on Washington St.