George St Bypass Stormsewer Project

This project includes installation of approximately 1,800 feet of 42-inch diameter storm sewer along George St from the existing culvert under George St to Redmond Reservoir. The project also includes installation of smaller storm sewer later pipes ranging from 12 to 24-inch in diameter.

Other major work items include storm sewer removal, pavement removal, resurfacing George St within project limits, spot sidewalk replacement, and spot curb and gutter replacement. Miscellaneous items of work include replacement of sanitary service adjustments, water service adjustments and landscape restoration.

The project is anticipated to begin on April 9, 2018 and has a completion date of June 30, 2018.

For the project duration, George St, within the project limits will be limited to Eastbound traffic only. The westbound traffic will be detoured to Jefferson St. Please see attached map.

George St Bypass - Information Letter 1 - Construction Phase

George St Bypass - Detour Map

04/20/2018 Update

As of now, the contractor plans to tentatively start this project on May 7, 2018.

04/13/2018 Update

As of now, the contractor plans to tentatively start this project on May 1, 2018.