UPDATE: During the week of May 28, the contractor finished milling all of the existing surface. Due to wet weather, the contractor was only able to perform limited patching this week. They also performed crack filling and paving the binder layer from Jacquelyn Dr to approximately Red Oak Ave. Weather permitting, the week of June 3rd, the contractor will continue paving the binder all the way up to Green St. It is also possible they will begin structure adjustments during the latter half of the week. During these operations the traffic will be heavily impacted and will cause long delays. Please utilize alternate route options if possible.