Posted on: July 29, 2020

Metra / Addison Crossing Repair: 8/5-14

Metra_02

Metra is planning to perform crossing repair work at Addison St between Aug 5-14, 2020. This crossing will be closed during that time. Below is the timeline provided for the work and attached is a detour plan. The detour will be using Center St.  All work is weather permitting.

  • Wednesday 8/5/20 – Close the road crossing and saw-cut pavement
  • Thursday/Friday - Remove the asphalt and crossing rubber
  • Saturday/Sunday - Replace the tracks
  • Monday - Final track adjustments
  • Tuesday/Wednesday – install our new standard crossing concrete pads instead of the existing rubber
  • Thursday - Asphalt
  • Friday 8/14/20 – Open the road crossing