The Village of Bensenville will be resurfacing Jefferson St between Church Rd and County Line Rd this Spring/Summer. This project is 70% funded by the federal grant monies, while the remainder 30% is local agency responsibility. The tentative start date for this project is April 27, 2015 and the completion date is set for June 30, 2015. Other items of work include spot curb and gutter removal and replacement, pavement patching, traffic detector loops, pavement striping, structure adjustments, etc. At this point, no permanent closures and/or detours are anticipated during construction. However, motorists are advised to proceed with caution as there will be temporary traffic delays as well as temporary driveway closures during construction. Please refrain from parking on the street during the construction. Should you need additional information, please contact Engineering Division within Public Works Department at 630-350-3435.